|
The Parsons Lake natural gas field is in the Mackenzie Delta,
about 75 kilometres northeast of Inuvik and about 55 kilometres southwest
of Tuktoyaktuk. This natural gas reservoir is about three
kilometres below the surface.
The Parsons Lake gas field is held 75% by ConocoPhillips and 25% by ExxonMobil.

click for larger version (47.3 Kb)
Artists conception at this
time
click for larger version (55.8 Kb)
Artists conception at this
time
The Parsons Lake field has two main development
areas: the north pad and the south pad. The north pad is located
at the north end of Parsons Lake and will be the largest pad,
containing wells and a gas conditioning facility. The conditioning
facility will separate the natural gas, natural gas liquids
(NGL) and water. Then, dehydrators will dry the gas and the
NGLs and a cooling system will chill them both. The dry and
chilled gas and NGLs can then be placed in a buried pipeline.
This pipeline goes from the north pad to the Storm Hills junction
of the Mackenzie Gas Project Gathering System. In the future,
compression will be added at the north pad to 'push' the gas
into the pipeline. The south pad is located in south of Parsons Lake and will be a small pad containing only wells
and a heater. The south pad will be built later as its production
will be used to keep the north pad gas conditioning facility
operating at full capacity. The production from the south
pad consists of natural gas, NGLs and water. Because of the
water, a heater is needed to keep the production flowing
and the flow line from the south pad to the north pad will
be an elevated, above ground line. The flow line will be in the same
right of way as the buried pipeline from the north pad.
A number of wells will need to be drilled to
produce the natural gas from the Parsons Lake field. The wells will
be drilled directionally from the north and south pads to
lessen the amount of land disturbed. In addition, both pads
will be constructed on areas that were previously old well
sites from the 1970s. However, in the future it may be necessary
to construct a satellite well pad or pads to reach natural gas not
accessible from either of the two initial pads.
Subject to regulatory approval, construction of the north
pad site is expected to start within 4 to 7 years. Drilling would start and continue 2 to 4 years after. Field production
is targeted to begin once other components are completed. There will be construction
and drilling in the future for the south pad and north pad compression
facilities.
back | top
|